Installation
The installation are finished on time. Big thank you to everybody involved.
The information and photos here below are coming mainly from E. Siesling and P. Delahaye.
Comments are added each day after the information from Erwin, Jerome and Pierre.
The reference measurements for the two triplets and the RFQ were performed by Erwin, Magnus and Jerome.
- On Tuesday the 2nd of October the the vacuum in the beam line section has been set to
atmosphere and the old beam line section has been removed.
- Jerome has finished the measurements in the HRS.VS30 zone.
- The difficulties of getting the vacuum system running after closing the switchyard was solved. Thanks to the vacuum support group.
The three chassis with Q1, Q2 and the RFQCB have been installed. Please see figures below:
The table below is the day to day planning during the
inatallation .
WHAT/td>
|
WHO |
WHEN |
COMMENT |
Finish connecting the electrodes |
Pierre & Pascal |
Tuesday to Friday |
DONE |
Finish the missing connector: |
Hanna & Ermano |
Tuesday |
DONE
|
Assembly and fiducialisation of RFQ in 170
extension: |
Jerome and Erwin |
Thursday, Friday and Monday |
DONE |
Week 40 |
|
|
|
No beam on HRS |
|
Of Monday |
|
|
|
|
|
Measure the activity in the beam line area |
Alexandre Dorsival |
Monday |
DONE |
Take out the existing beam-line |
Erwin, Jerome
and Ermano, Pierre |
Tuesday afternoon |
DONE |
The three support tables will be installed
and markings on the floor need to be made |
Erwin, Jerome
and Magnus, Pierre |
Wednesday |
DONE |
Drilling of holes |
Ermano, ? |
Thursday |
DONE |
Positioning of table fixations |
Ermano, Jerome, Erwin,
Magnus, Pierre |
Thursday |
DONE |
Mechanical alignment of the three tables |
Erwin, Jerome
and Magnus, Pierre |
Thursday |
DONE |
Fine adjustment of the alignment |
Jerome, Erwin and Magnus |
Friday |
DONE |
WEEK 41 |
|
|
|
Continue the fine adjustment of the
alignment |
Jerome, Erwin and Magnus |
Monday-Wednesday |
DONE |
Connections of electronics |
J. Parra-Lopez
and N. David |
Monday-Friday |
DONE |
WEEK 42 |
|
|
|
GPS OFF ACCESS TO HRS SEPARATOR ZOONE |
A. Dorsival |
Monday morning |
|
Connections of vacuum |
ATB-IF |
Monday-Friday |
DONE |
Compressed air installation. |
ATB-IF |
Monday, Thursday-Friday |
DONE |
Installation of water cooling |
Stephano and Jerome |
Friday |
DONE |
WEEK 43 |
|
|
|
Installation of the Boris tube |
|
Monday |
DONE |
Testing of vacuum pumping the RFQ section |
ATB-IF, Sophie, Henrik, David ? |
Monday, Tuesday |
DONE |
Installation of cage around the RFQ |
Stephano and Jerome |
Tuesday-Wednesday |
DONE |
WEEK 44 |
|
|
|
Security check of the HT |
|
Monday |
DONE |
Power up the RFQ |
Pierre, N. David, Hanna |
Tuesday-Wednesday |
DONE |
Start with tests |
Pierre, Hanna |
Wedneday-Friday |
DONE |
Pictures from the installation of HV platform are found under
Photographs.
Some additional pdf documents with more photos for the progress by E. Siesling
is found here:
Summary HV platform.
Summary HV platform 2nd stage.
Summary fiducialisation.
Summary installation 22 of October
|