Installation

The installation are finished on time. Big thank you to everybody involved.

The information and photos here below are coming mainly from E. Siesling and P. Delahaye. Comments are added each day after the information from Erwin, Jerome and Pierre.
The reference measurements for the two triplets and the RFQ were performed by Erwin, Magnus and Jerome.

  • On Tuesday the 2nd of October the the vacuum in the beam line section has been set to atmosphere and the old beam line section has been removed.
  • Jerome has finished the measurements in the HRS.VS30 zone.
  • The difficulties of getting the vacuum system running after closing the switchyard was solved. Thanks to the vacuum support group.

The three chassis with Q1, Q2 and the RFQCB have been installed. Please see figures below:
  
 

The table below is the day to day planning during the inatallation .

WHAT/td>

WHO

WHEN

COMMENT

Finish connecting the electrodes

Pierre & Pascal

Tuesday to Friday

DONE

Finish the missing connector:

Hanna & Ermano

Tuesday

DONE

 

Assembly and fiducialisation  of RFQ in 170 extension:

Jerome and Erwin

Thursday, Friday and Monday

DONE

Week 40

 

 

 

No beam on HRS

 

Of Monday

 

       

Measure the activity in the beam line area

Alexandre Dorsival

Monday

DONE

Take out the existing beam-line

Erwin, Jerome and Ermano, Pierre

Tuesday afternoon

DONE

The three support tables will be installed and markings on the floor need to be made

Erwin, Jerome and Magnus, Pierre

Wednesday

DONE

Drilling of holes

Ermano, ?

Thursday

DONE

Positioning of table fixations

Ermano, Jerome, Erwin, Magnus, Pierre

Thursday

DONE

Mechanical alignment of the three tables

Erwin, Jerome and Magnus, Pierre

Thursday

DONE

Fine adjustment of the alignment

Jerome, Erwin and Magnus

Friday

DONE

WEEK 41

 

 

 

Continue the fine adjustment of the alignment

Jerome, Erwin and Magnus

Monday-Wednesday

DONE

Connections of electronics

J. Parra-Lopez and N. David

Monday-Friday

 DONE

WEEK 42

 

 

 

GPS OFF ACCESS TO HRS SEPARATOR ZOONE

A. Dorsival

Monday morning

 

Connections of vacuum

ATB-IF

Monday-Friday

DONE

Compressed air installation.

ATB-IF

Monday, Thursday-Friday

DONE

Installation of water cooling

Stephano and Jerome

Friday

DONE

WEEK 43

 

 

 

Installation of the Boris tube   Monday DONE

Testing of vacuum pumping the RFQ section

ATB-IF, Sophie, Henrik, David ?

Monday, Tuesday

DONE

Installation of cage around the RFQ

Stephano and Jerome

Tuesday-Wednesday

DONE

WEEK 44      
Security check of the HT   Monday DONE

Power up the RFQ

Pierre, N. David, Hanna

Tuesday-Wednesday

 DONE

Start with tests

Pierre, Hanna

Wedneday-Friday

 DONE


 

Pictures from the installation of HV platform are found under Photographs.

Some additional pdf documents with more photos for the progress by E. Siesling is found here: Summary HV platform. Summary HV platform 2nd stage. Summary fiducialisation. Summary installation 22 of October


Last updated 12.11.2008 by Hanna Franberg